Study Of The Potential For Floating Solar Power Plant In Situ Gede Bogor City
Abstract
Floating Solar Power Plant utilized in research is located in Situ Gede Bogor City. The utilization of the situ area which has a land area of . With a power plant area utilization plan of 1 Hectare the potential average solar radiation at Situ Gede is . The total energy generated is . This research uses a Interactive Microgrid as a solar power system configuration scheme. The components used are Monocrystalline solar modules with a capacity of 500 Wp totaling 4200 units, 22 inverter units with a capacity of 2458 kW, a battery unit value the total capacity is 3634,634 kW with a total of 1818 battery units, and the battery inverter capacity of 25000 W, with a total battery inverter capacity value of 8034,78 kW, which is the total use of 3 battery inverter units. The simulation results on PVSyts obtained the value of solar power plant in one year is 3148720 kWh a Performance Ratio of 84.48% and a Capacity Factor value of 17.19%. With a total initial investment cost of Rp85.033.240.352, the Payback Period is obtained in a period of 11 years with an estimated operating time of 20 years.
Full Text:
PDF(81-87)References
W. Nandini and B. Sutanto, “Model Adaptasi Penggunaan Teknologi Baru Pembangkit Listrik Tenaga Surya ‘ Ecotechnology dan Pemberdayaan Masyarakat untuk Indonesia Berdaya dalam Menghadapi Perubahan Iklim ’ Dilakukan secara daring , 7 November 2020,” Pros. Semin. Nas. Adiwidya 8 Pascasarj. ITB, vol. 8, no. 1, 2021.
Rahman, “Potensi Pengembangan Situ Di Kota Bogor Sebagai Objek Wisata,” 2010.
I. G. Ngurah and A. Dwijaya, Draft Buku Ajar Pemnangkit Listrik Tenaga Surya, no. September. Bali: Teknik Elektro. Polteknik Negeri Bali, 2019.
M. Gumintang, M. Sofyan, and I. Sulaeman, Design and Control of PV Hybrid System in Practice. Jakarta, 2020.
F. Yahya, “Perencanaan Pembangkit Listrik Tenaga Surya Terapung (Floating Solar Photovoltaic) Di Situ Gede Kota Tasikmalaya,” Universitas Siliwangi, 2023.
Kementerian PUPR, Peraturan Menteri PUPR Republik Indonesia Nomor 7 Tahun 2023 Tentang Perubahan Kedua Peraturan Menteri PUPR Nomor 27/PRT/M/2015 Tentang Bendungan. Indonesia, 2023, pp. 1–27.
N. Taylor, Guidelines for PV Power Measurement in Industry. 2010.
A. Z. Standard, Stand-Alone Power Systems Part 2 : System Design, vol. 2. Australian, 2010.
Noer Soedjarwanto, Endah Komalasari, and Syuja Asyraf Fardhan, “Studi Kelayakan Pembangkit Listrik Tenaga Surya (PLTS) Dengan Baterai Dan Terhubung Grid Di Nias Sumatera Utara,” J. Tek. Ilmu Dan Apl., vol. 3, no. 2, pp. 1–7, 2022, doi: 10.33795/jtia.v1i1.91.
R. P. Arinata and T. H. Akram, “Analisis Pengembangan PLTS Di Pulau Takabonerate,” J. Multidisiplin Saintek, vol. 2, no. 4, 2024.
R. Rafli, J. Ilham, and S. Salim, “Perencanaan dan Studi Kelayakan PLTS Rooftop pada Gedung Fakultas Teknik UNG,” Jambura J. Electr. Electron. Eng., vol. 4, no. 1, 2022, doi: 10.37905/jjeee.v4i1.10790.
E. A. Karuniawan, “Analisis Perangkat Lunak PVSYST, PVSOL dan HelioScope dalam Simulasi Fixed Tilt Photovoltaic,” J. Teknol. Elektro, vol. 12, no. 3, 2021, doi: 10.22441/jte.2021.v12i3.001.
Ortax, “Kurs Bank Indonesia terhadap USD Amerika Serikat.” Accessed: Jul. 09, 2024. [Online]. Available: https://datacenter.ortax.org/ortax/kursbi/show/USD
F. Hidayat, B. Winardi, and A. Nugroho, “Analisis Ekonomi Perencanaan Pembangkit Listrik Tenaga Surya (PLTS) Di Departemen Teknik Elektro Universitas Diponegoro,” Transient, vol. 7, no. 4, 2019, doi: 10.14710/transient.7.4.875-882.
M. Elena, “Rapat Dewan Gubernur (RDG) Bank Indonesia Putuskan BI Rate Juni 2024, Ekonomi Proyeksi Tetap.” Accessed: Jul. 22, 2024. [Online]. Available: https://finansial.bisnis.com/read/20240619/11/1775322/rapat-dewan-gubernur-rdg-bank-indonesia-putuskan-bi-rate-juni-2024-ekonom-proyeksi-tetap
H. Maruta, “Analisis Break Even Point (BEP) Sebagai Dasar Perencanaan Bagi Manajemen,” J. Akuntasi Syariah, vol. 2, no. 1, 2018.
DOI: https://doi.org/10.37058/jeee.v6i1.12301
Refbacks
- There are currently no refbacks.
Journal of Energy and Electrical Engineering (JEEE)
Program Studi Teknik Elektro Fakultas Teknik Universitas Siliwangi
Jl. Siliwangi No. 24 Kota Tasikmalaya - 46115
email: jeee@unsil.ac.id
e-ISSN: 2720-989X
INDEXED BY: